OPS HubOPS Academy · free for everyone Sign in

US central office & core network

The active network: OLTs, ODFs, aggregation, BNGs, core and edge routers, CO power and cooling.

Overview

The central office (CO) houses the active network. Outside-plant fiber terminates on the optical distribution frame (ODF), where it is patched to OLT PON ports. Each OLT port serves many homes through splitters and handles ONT authentication, bandwidth, service profiles and VLANs. OLT uplinks feed aggregation routers and switches, which collect traffic from many OLTs with redundant links so one failure does not take an area down. Broadband network gateways (BNGs) handle subscriber sessions, IP addresses and policies. Aggregation connects to the metro and core networks — high-capacity routers on 100–800 Gbit/s links, often over DWDM optical transport — and the internet edge routers exchange routes with transit providers, internet exchanges and content networks using BGP. All of this runs on DC power from rectifiers with battery strings and a standby generator, and cooling that keeps the room in range.

Jobs this covers

us_olt, us_odf, us_agg, us_edge, us_bng, us_co_power, us_hvac — certificate: US central office & NOC (required)

The equipment — what everything does

OLT (optical line terminal)

Lights the PON, authenticates ONTs and applies service profiles. Multiple PON ports per shelf.

In game: /towers → OPS America Fiber → Central office · optical & routing → OLT.

ODF (optical distribution frame)

Terminates, organises and patches outside-plant fiber to equipment.

In game: Central office · optical & routing → ODF.

Aggregation / core router

Collects OLT traffic and carries it across the metro and core with redundancy.

In game: Central office · optical & routing → Aggregation / core router.

Internet edge router / BNG

BGP to transit and peering; subscriber sessions, IP assignment and policies.

In game: Central office · optical & routing → Edge router / BNG.

DC power plant

Rectifiers turn AC into -48 V DC; batteries carry the load in an outage; a generator takes over for long ones.

In game: Central office · power & HVAC.

HVAC

Indoor cooling and an outdoor condenser keep the equipment room in temperature range.

In game: Central office · power & HVAC.

Tools & PPE

Engineer laptop & console cable

Configures routers, NVRs and servers, runs speed tests and opens OPS Hub.

Optical light meter / OTDR

Measures how much light arrives down a fibre, and where along it a break or bad splice is.

ESD wrist strap PPE

Grounds you so static electricity doesn't destroy server and network boards.

Torque driver

Tightens electrical terminals and rack rails to the correct torque — not too loose, not stripped.

Label printer

Labels both ends of every cable and port so the next engineer knows what is what.

Multimeter / voltage tester

Proves a circuit is dead before you touch it, and measures voltage, continuity and resistance.

Lock-off kit

Padlocks and tags that stop anyone switching a circuit back on while you work on it.

ESD wrist strap PPE

Grounds you so static electricity doesn't destroy server and network boards.

Safety glasses PPE

Protect your eyes from fibre shards, drilling dust and laser light.

Insulated gloves PPE

Rated gloves for work near live electrical parts and for sharp metal edges.

Standalone servers: tools are in your van (OPS Work → My van & tools). Items servers: collect them — and the job’s parts — at an OPS depot.

Step by step

1
Plan the change

Check the design, rack space, power budget and a maintenance window with the NOC.

Engineer laptop & console cable NOC / OPS Hub clipboard
2
Rack and earth

Rack the equipment, bond it to the CO earth, wear your ESD strap.

ESD wrist strap Equipment room reach
3
Power it

Land -48 V DC from the power plant on the right breaker; lock-off while you work.

Lock-off kit DC power plant kneel
4
Patch the fiber

Patch from the ODF to the OLT PON ports or router optics; clean and inspect every connector.

Optical light meter / OTDR ODF inspect
5
Label everything

Label ports, patches and circuits and update inventory.

Label printer Equipment room type
6
Turn up

The NOC loads the configuration, checks alarms, optics and traffic, and brings up redundancy.

Engineer laptop & console cable With the NOC type

Health & safety

DC power and batteries

Risk: Battery strings can deliver huge currents — burns and arc flash.

Control: Insulated tools, lock-off, no jewellery, eye protection.

Static discharge

Risk: ESD destroys line cards and optics.

Control: Wear an ESD wrist strap when handling cards.

Laser light

Risk: High-power optics can damage eyes.

Control: Never look into ports or patch cords.

Lifting

Risk: Heavy shelves and batteries cause injuries.

Control: Two-person lifts and lifting aids.

In game you confirm these in a risk assessment before starting. Skipping them on risky work can cause a fall or a shock — and it’s logged as a safety incident.

When it’s not done correctly

Patching the wrong ODF port

A whole neighbourhood lands on the wrong OLT port — nobody activates.

No redundant uplink

One link failure takes the whole area offline.

Generator not tested

Batteries run flat in a long outage and the CO goes dark.

Cooling failure ignored

Equipment overheats and shuts down.

Changes outside a maintenance window

Unplanned outage for thousands of customers.